County Road 21 Tentative Schedule

April 19 – Project Surveying beings (Road remains open)

May 10 – Contactor will set up equipment for paving and the road will be CLOSED TO THRU TRAFFIC

May 17 – Road will be closed and paving begins

June 18th – Expected Completion Date